NCWSP

Project Description:

Development of new water source (600mld) in order to meet the increasing water demand by constructing a redundant dam for Metro Manila’s domestic water supply.

Location:

Brgy. Pagsangahan, General Nakar, Quezon / Brgy. Magsaysay, Infanta, Quezon

Project Cost:

PhP 18.724 Billion

Funding Source:

Private Sector through PPP

Status:  (as of 31 December 2016)

  • On-going coordination with DPWH relative to the signing of MOA for the joint implementation of the Project.
  • Bidding documents were already completed but still to be approved by the Joint Special Bids and Awards Committee (JSBAC) and the new MWSS Board (still to be appointed by the President).
  • On-going coordination with the other LGUs relative to their endorsements of the Project, including with the NCIP & PAMB for the required clearance.

 

NCWSP3

The proposed New Centennial Water Source Project (NCWSP) will provide water security, reliability and additional supply for Metro Manila.  It is planned to be site specific, zeroing in on the Kaliwa-Kanan-Agos River Basin as an alternative water source.

The NCWSP will involve the construction of a dam at the Kaliwa River (Laiban Dam), and a smaller dam (Kaliwa Dam) downstream to maximize the water supply, and to ensure short and long term supply for Metro Manila and its adjoining areas.